
Lynchburg Construction Attorneys
PLDR Law's construction practice serves regional and national contractors, subcontractors, suppliers, and developers — including projects across Central Virginia and the Mid-Atlantic. The team handles contracts, claims, surety work, mechanic's liens, and project disputes from form-of-contract through final closeout.
What the PLDR construction team handles
Construction matters move fast and carry hard deadlines. PLDR's construction practice is built around contractors and developers who need substantive legal work the same week — not weeks later. The team works alongside PLDR's surety, real-estate, business-formation, and civil-litigation groups so contract questions, lien questions, and dispute questions can all be answered from the same firm.
Contracts & pre-project
- AIA contract review, customization, and negotiation (A101, A102, A103, A201)
- ConsensusDocs and EJCDC form review
- Owner-contractor and contractor-subcontractor agreements
- Master subcontract agreements, scope of work, and flow-down language
- Indemnity, insurance, and additional-insured analysis
Project representation & counseling
- Change-order management, RFIs, and notice provisions
- Differing site condition claims under federal and Virginia state contracts
- Schedule and delay claim analysis
- Pay-when-paid and pay-if-paid issues in Virginia subcontracts
- OSHA, prevailing wage, and Virginia Department of Labor & Industry questions
Disputes, liens, & collections
- Virginia mechanic's liens under Va. Code § 43-1 et seq. — perfecting, enforcing, defending
- Payment and performance bond claims (state-bonded jobs and Miller Act federal claims)
- Construction litigation in Virginia circuit courts and the U.S. District Court for the Western District of Virginia
- Arbitration under AAA Construction Industry Rules and other arbitral panels
- Mediation and other forms of negotiated resolution
Virginia mechanic's lien deadlines — short and unforgiving
Mechanic's liens are the single most powerful — and most easily lost — tool for contractors and suppliers in Virginia. The deadlines are short and there is no grace period.
- Memorandum of Lien must be recorded in the appropriate circuit court clerk's office within 90 days of the last day of the month in which the lienor last performed work or furnished materials — and not more than 90 days after the work was performed or the materials furnished.
- Suit to enforce the lien must be filed within six months of recording (or within 60 days of completion of the entire structure, whichever is later).
- Notice requirements differ for general contractors, subcontractors, and material suppliers — and missing notice can void the lien.
If a lien deadline is approaching, call PLDR. We will tell you immediately what's perfectible and what isn't.
Surety & bond claim work
PLDR's surety practice is one of the few regional firms with deep experience on both sides of bond claims — representing sureties on payment, performance, and miscellaneous bonds, and representing claimants seeking payment under bonded contracts.
- Miller Act claims on federal projects (40 U.S.C. § 3131 et seq.)
- Little Miller Act claims on Virginia public projects under the Virginia Public Procurement Act
- Private-project payment bond claims
- Performance bond defaults and takeover
- License bonds, court bonds, and miscellaneous surety matters
Where PLDR's construction work happens
The Lynchburg office serves construction clients across Central Virginia, with regular project work in Campbell, Amherst, Bedford, Appomattox, Nelson, and Pittsylvania counties — plus the City of Lynchburg's downtown and riverfront redevelopment corridors. Many PLDR construction clients work on multi-state portfolios; the firm coordinates Virginia work with local counsel in adjacent states as needed.
This page provides general information about Virginia construction law and PLDR Law's construction practice. It is not legal advice and does not create an attorney-client relationship. Lien and bond deadlines are strict; do not rely on this page for specific deadline calculations.

The PLDR construction team.
Andrew leads the construction practice, including bond claims and contractor representation. Scott handles surety and complex construction disputes. Mark works the transactional side — contracts, development agreements, and project structuring.

Andrew P. Pearson
Ethics Counsel · Head of Construction SectionAssists clients with complex construction law and litigation issues.
View profile →
Scott W. Kowalski
Chair of the Board of DirectorsCounsels construction industry clients on construction contracts, claims, and disputes.
View profile →
Mark A. Burgin
AttorneyHandles commercial real estate transactions, business formations, mergers and acquisitions, construction contracts, and the disputes that occasionally come with them.
View profile →
On the practice
One call puts your matter in front of the right team.PLDR Law · Lynchburg
Common questions.
Construction matters have deadlines. We track them.
If a lien deadline, change-order dispute, or bond claim is on the horizon, call PLDR's Lynchburg office and we'll tell you what to do — fast.
Not legal advice. The information on this page is general and is not, nor is it intended to be, legal advice. You should consult a PLDR Law attorney for individual advice regarding your situation. Visiting this site or contacting the firm does not create an attorney-client relationship.